# Mid-Scale Solar STCs: Retailer Checklist | ArcSolar

> Eligible mid-scale solar installed from 1 October 2026 can use the expanded SRES. Check application timing, commissioning evidence and quote assumptions.

Canonical: https://www.arcsolar.com.au/resources/mid-scale-solar-stc-retailer-checklist  
Last updated: 2026-10-06

Industry updates · By Argonix Digital · Published 2026-10-06 · Updated 2026-10-06

**Key point:** Prepare the commissioning and approval evidence now. Confirm the application opening before lodging, and avoid promising a settlement date.

## Which systems does the change cover?

CER’s transitional guidance defines mid-scale eligibility as greater than 100kW and up to 1MW, subject to the other requirements. Eligible systems use a fixed five-year deeming period. CER also describes an STC/REGO choice; choosing STCs prevents REGO creation during that deeming period.

Sources: [Mid-scale solar changes apply from 1 October 2026](https://cer.gov.au/news-and-media/news/2026/october/changes-to-mid-scale-solar-apply-today); [Mid-scale solar eligibility and application timing](https://cer.gov.au/schemes/renewable-energy-target/small-scale-renewable-energy-scheme/small-scale-renewable-energy-systems/mid-scale-solar); [Transitional guidance for mid-scale solar PV systems](https://cer.gov.au/document/transitional-guidance-mid-scale-solar-pv-systems)

## Prepare an evidence handover

- Confirm the system boundary and existing or related generation before choosing a certificate route.
- Retain applicable planning/building and network approvals, design and metering records, and the electrical compliance certificate.
- Record testing and commissioning. CER uses when the system first becomes capable of producing and delivering electricity, rather than the procurement date.
- Give the installer and registered agent clear ownership of serial-number and photographic evidence.

Sources: [Transitional guidance for mid-scale solar PV systems](https://cer.gov.au/document/transitional-guidance-mid-scale-solar-pv-systems)

## Example: an October commissioning date

Illustrative example: a 150kW project is planned for commissioning on 20 October. The team checks eligibility, retains approvals and records the actual commissioning evidence. The offer explains that applications are expected later in November; neither the planned install date nor a prepared evidence pack proves approval or payment.

| Milestone | What to record |
| --- | --- |
| Commissioning | Actual date and compliance evidence |
| Application opening | Current CER process and outstanding requirements |
| Settlement | Confirmed financial evidence |

## Check extensions and scheme interactions

Related systems, upgrades and existing accredited power stations need a specific eligibility assessment. Use CER’s current transitional guidance and your agent’s advice. This guide does not calculate certificate value or establish ArcSolar support for a 1MW design or mid-scale claim submission; confirm those requirements separately.

Sources: [Transitional guidance for mid-scale solar PV systems](https://cer.gov.au/document/transitional-guidance-mid-scale-solar-pv-systems)

## Agree the next action before handover

Use an ArcSolar demo to follow the customer, quoted scope and installer handover together. Bring the commercial connection and claim requirements so the team can confirm your setup.

- [Review the network export checklist](https://www.arcsolar.com.au/resources/solar-export-limit-proposal-checklist)
- [Prepare the installation handover](https://www.arcsolar.com.au/resources/solar-installation-readiness-checklist)
- [Review ArcSolar plans and setup](https://www.arcsolar.com.au/pricing)

Sources: [ArcSolar field work and installer handover](https://docs.arcsolar.com.au/delivery/field-operations)

## Sources

- [Mid-scale solar changes apply from 1 October 2026](https://cer.gov.au/news-and-media/news/2026/october/changes-to-mid-scale-solar-apply-today) (Clean Energy Regulator, checked 2026-10-06)
- [Mid-scale solar eligibility and application timing](https://cer.gov.au/schemes/renewable-energy-target/small-scale-renewable-energy-scheme/small-scale-renewable-energy-systems/mid-scale-solar) (Clean Energy Regulator, checked 2026-10-06)
- [Transitional guidance for mid-scale solar PV systems](https://cer.gov.au/document/transitional-guidance-mid-scale-solar-pv-systems) (Clean Energy Regulator, checked 2026-10-06)