Solar export limits: a retailer’s proposal checklist

Check network export, inverter capacity and portal dates before quoting. Separate Ausgrid Connect, CER registration and backstop testing, and prepare installer training.

Gather five things before issuing the offer

  • Confirm the installation address, NMI, distributor and supply phases against the customer’s evidence.
  • Record panel capacity, combined solar/battery inverter ratings and the requested export limit separately.
  • Keep the current network offer, reference, approved export limit and any stated conditions or expiry.
  • Check compatible equipment, internet requirements and who will complete commissioning and metering steps.
  • Review savings assumptions and give every unresolved condition an owner before handover.

Sources: [1][2][3]

ArcSolar’s Site Information Form collects the bill, switchboard photos and cable-run video. Review the uploads before quoting; a submitted form does not approve a grid connection.

Check the distributor’s current rules

AusNet’s up-to-30kW guidance requires pre-approval before installation and assesses combined solar and battery inverter ratings. The offer records the permitted generation and export limits; available export capacity can change.

Ausgrid now lists separate dates for portal registration and emergency-backstop testing. Check the site's network, application dates and postcode before promising readiness. An approved export limit remains a ceiling, not guaranteed output.

Sources: [1][6]

NSW: use the CER Installer Portal by network and application date

Ausgrid Connect launches on 23 November for Embedded Generation applications only; other connection work stays in current systems until a later release. It is separate from the NSW CER Installer Portal, which handles eligible installation registration and commissioning.

The NSW CER Installer Portal launched in November. For new or upgraded systems up to 200 kW, portal requirements apply to connection applications submitted and approved from 2 November for Endeavour Energy, and from 23 November for Ausgrid and Essential Energy. Check both dates against the job’s distributor and application record.

The NSW Government’s free self-paced portal user module takes about 60 minutes and earns 10 CPD points. A separate awareness module covers Minimum System Load, the Emergency Backstop Mechanism and portal rollout; it takes about 45 minutes and earns 20 CPD points.

For newly installed rooftop systems registered through the portal, installers must check internet communication with the DNSP utility server. NSW says a low default export limit applies where a premises lacks reliable internet until connectivity is available.

NSW: use the CER Installer Portal by network and application date
NetworkDNSP connection application submitted and approved from
Endeavour Energy2 November 2026
Ausgrid and Essential Energy23 November 2026

Sources: [4][5][6][7]

NSW says there is no fee to register or submit through the CER Installer Portal, but DNSP application fees still apply. Emergency Backstop Mechanism enablement is a separate rollout through 2027 and will not apply to every installation at portal launch. In Ausgrid’s network, postcode-based capability tests start on 30 November; the network lists 22 February 2027 for all new and upgraded systems to be registered and backstop-enabled.

For eligible work, the portal handles the Certificate of Compliance for Electrical Work (CCEW) and DER Register information. Other electrical work on the same job still needs a separate CCEW through BCNSW eCert. Name the person responsible for each submission and keep the completion records with the job.

Example: 10kW inverter, 1kW export offer

Illustrative example: a single-phase customer has a proposed 10kW inverter and a network offer allowing 1kW export. Record both values. The 1kW limit constrains export power; it does not mean the system generates only 1kW or exports 1kWh each day.

Example: 10kW inverter, 1kW export offer
EvidenceNext action
Network offer: 1kW exportConfirm equipment and conditions
Proposal assumes export incomeReview the energy and tariff assumptions
Commissioning still pendingKeep readiness unresolved; assign an owner

Keep approval and estimates separate

Rules vary by network, site and connection type. A flexible maximum may be reduced as network conditions change. This checklist does not replace the connection agreement or installer assessment. ArcSolar’s savings estimate needs reviewed inputs; automatic enforcement of a distributor’s export limit in the estimator is not established here.

Sources: [6][3]

Walk one connection condition through the quote

Bring the network offer and one proposal to an ArcSolar demo. Review the site evidence, customer assumptions and the next handover action together.

Sources and review (7)

Published by ArcSolar. Examples are illustrative; product details come from the sources below. Editorial standards.

Put the workflow to work.

Connect site evidence to the customer proposal

Book a demo